Week 23

Walls are primed; tile and floors are nearly done; kitchen appliances were delivered today–to be installed this week!

There were several more mishaps and surprises this week—like, oh, the kitchen is 5 inches shorter than the drawings allowed for—which means Chris had to make two trips to Ikea in one day to get a new sink and cabinet that would fit. Then there was a lack of communication between project manager and flooring guys, which resulted in the guys having to pull up some of what they had already done and do it again (mind you, all of this was in the specs from the beginning!).

On the bright side, things are looking good, and my wonderful, supportive parents are coming this weekend to help us paint the ceilings and maybe work on the fence.

I have even started packing!

First Floor

First Floor

Second Floor

Second Floor

Second Floor Bathroom

Bathroom tile

Bathroom tile

kitchen2

Kitchen

Kitchen

One comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s